| Date |
Activity |
| 9-27 |
- Dan work, on updating Authority's emergency response plan.
- Haul 1B stone and screenings to use as fill around piping at stp.
- Get 4 rear tires put on garbage truck.
|
| 9-28 |
- Work on water meters around town that need repaired.
- Install 12" DIP bypass around old CL2 pit.
- Paint top portion of trickling filter inside wall.
- First budget meeting for 2003.
|
| 10-1 |
- Receive State Allocation for pension funds.
- Start installing electrical conduit at stp.
- Put second coat of paint on inside wall of trickling filter.
|
| 10-2 |
- Three employees go to sewer class in morning, at Wellsboro.
- Install electrical conduit at stp. Borrow Mike Stoudt's portable heater to use for bending pipe around corners.
- Dave Jones at stp to check out electrical system .
- Hydro at old NPHC well to check out flows. Preliminary estimates of a safe yield of 50 GPM. I will contact Authority engineer.
|
| 10-3 |
- Cut posts to support distributor arm at stp trickling filter.
- S. Bray at stp in morning to help us set center hub for trickling filter. Install distributor arms in afternoon.
|
| 10-4 |
- Install electrical conduit at stp.
- Work on leveling trickling filter distributor arms.
- Take some picnic tables down town for Octoberfest.
- Mail pension funds from state to appropriate accounts.
|
| 10-6 |
- Level up distributor arms for trickling filter.
|
| 10-7 |
- Double check trickling filter distributor arm elevations then grout under center hub of distributor.
- Winterize softball and pool restrooms.
- Install electrical conduit at stp.
- Recreation meeting at school library. Stuff envelopes for United Fund.
|
| 10-8 |
- Three employees off sick today.
- Yearly calibration of source water meters completed today.
- Remove blocking from trickling filter and start cleaning up floor of filter.
|
| 10-9 |
- Two employees go to sewer class in morning at Wellsboro.
- Mansfield Crane look at foot bridge so a price can be quoted for removal of bridge.
- Cut vent pipes for trickling filter then mount on inside wall.
- Start installing under drain and media on half of floor for trickling filter.
- Take layout switch and panel boxes to Jim Smith so he can make frame work to hold units.
|
| 10-10 |
- Finish installing under drain in trickling filter.
- Start hauling plastic media to stp from garage.
|
| 10-11 |
- Finish hauling media from garage to stp, then turn on sewer flows to trickling filter.
- Install recirculating pump and adjust valve so water pumping to trickling filter distributor all the time. This will help promote the growth of bacteria, which is needed for sewer treatment.
- Add bacteria packets to sewer flows to help growth on trickling filter media. Have to add bacteria every day.
|
| 10-14 |
- Paid holiday.
- Council meeting will reconvene on 10-28.
|
| 10-15 |
- Clean out sludge beds at stp.
- Representative from US Filter at stp in morning to check out operation of trickling filter distribution arm. Only had to make a few minor adjustments. Installation looked good to him.
- Budget meeting for 2003 at Boro Hall all morning.
|
| 10-16 |
- Three employees go to sewer class in morning at Wellsboro.
- Clean up area inside fence at stp.
- Get wiring for rear lights of 1 ton repaired.
|
| 10-17 |
- Work on electric and plumbing for manhole by secondary clarifier.
|
| 10-18 |
- Finish work on manhole by secondary clarifier.
- Trim brush along edge of Ruah St.
|
| 10-21 |
- Install frame work for electrical boxes to manhole at stp.
- Core 3 inch hole in top of sludge manhole lid for access to pump wires. Cement 2 inch conduit into hole.
|
| 10-22 |
- Finish conduit run from fitting we cemented in top of sludge manhole to panel box.
- Broke hydraulic hose on excavator while digging at stp. Will have NAPA make up a new one.
- Cut hole in wall of control house at stp to run electrical conduit through.
- Budget meeting in morning. Finalize proposed 2003 figures.
|
| 10-23 |
- Three employees go to sewer class in morning at Wellsboro.
- Put new hose on excavator in afternoon.
- Work on electrical sub panel in control house at stp.
- Leesa make out 50 - 48 hour notices to be taken around tomorrow.
|
| 10-24 |
- Repair curb box lids at intersection of Ruah and Seymour Sts.
- Piston cylinder housing split on excavator while operating at stp. Will call Allenwood Equipment for price of used housing.
- DEP at stp to check out progress of work done to plant.
- Look for water leak along creek behind low income on Taber St.
|
| 10-25 |
- Work on plumbing at Boro garage.
- Remove old telephone poles at park by football scoreboard.
- Pick up 36 x 36 inch panel box for stp electric.
|
| 10-28 |
- Install 14 tons of BCBC blacktop on streets around town.
- Dave Jones repair photo cell for Veteran's Monument lights.
- Reconvened Council meeting.
|
| 10-29 |
- Drill holes in bottom of 3 x 3 foot panel box for 1 and 2 inch conduits to connect to box.
- Install 10 tons of ID2 blacktop on Ruah, Seymour and Nevins Sts. Take roller back to Montoursville in afternoon.
- Calling for 2 to 4 inches of snow tonight. Put salt spreader on 1 ton.
- Leesa make out shut off notices.
|
| 10-30 |
- Employees go to sewer class in Wellsboro.
- Shut off delinquent customers.
- Mount 36 x 36 inch panel box to outside wall of control house and connect conduits to top and bottom of box.
- Zoning Hearing Board meeting at night.
|
| 10-31 |
- Dave Jones work with Boro crew at stp pulling wire in conduit.
- Work on Boro garage plumbing.
|
 |
|
George Lloyd Borough Manager
|