Date Activity
11-1
  • Work on garage plumbing.
  • Pick up load of coal for garage.
  • Remove broken cylinder from excavator and take to Allenwood for repair.
  • Pull wires into conduit for sludge manhole at stp.
  • Winterize multrum restrooms.

11-4
  • Talk to Authority engineer about NPHC well. Will discuss with Authority members at meeting tonight.
  • Put up voting booths in Council Room for Election tomorrow.
  • Major water leak in Morris Run. Send Boro crew to repair. Will rebill Morris Run for labor and equipment used.

11-5
  • Finish garage plumbing.
  • Install pump in sludge manhole and connect to piping.
  • Run waste water through new CI2 pit and plumb CI2 line to new pit for disinfection.

11-6
  • Sewer class at Wellsboro in morning.
  • Take down voting booths.
  • Run wire from outside panel box at stp to inside control building.
  • Start work on grant applications for footbridge replacement.

11-7
  • Finish winterizing Island Park pool and restroom behind Recreation Building.
  • Put picnic tables at park into pavilions.
  • Work on grant application for footbridge replacement. Cheryl Bubacz fill out grant application to Packer Foundation.
  • Haul 2 RC for stp to spread on access roads around plant.

11-8
  • Discuss footbridge abutments with engineer. He will quote me a cost estimate so it can be submitted with grant application.
  • Cleanup loose material lying around stp, while gravel is spread over access roads.
  • Order last two loads of salt for stockpile. Will be delivered next week.

11-11
  • Both loads of salt delivered today.
  • Allenwood Equipment replace cylinder on excavator.
  • Haul sludge from Sportsman's Well basement.

11-12
  • Finish hauling sludge from Sportsman's Well basement.
  • Put sawdust around pipes for drying beds at stp to keep from freezing this winter.
  • Street Committee meeting to look at Granger St. problems.

11-13
  • Sewer class at Wellsboro.
  • Clean up old stone and underdrain from trickling filter at stp.
  • Work on stp electric.
  • Mayor remove old wheels from cannon at Park and replace with different wheels.

11-14
  • Work on snow equipment.
  • Spread 2RC gravel on Granger St. cul-de-sac.
  • Spread gravel on access roads around stp.
  • Discuss new trickling filter media with company representative that Authority bought material from.

11-15
  • Finish spreading gravel on access roads around stp.
  • Add up costs Boro spent on new bleachers at Park, which can be applied toward grant funding.

11-16
  • Power outage in town. Call crew in to check out water and sewer plants.

11-18
  • Start cleaning up garages so equipment can be stored inside for winter.
  • Pull guys away from garage to work on water leak in Morris Run.

11-19
  • Water leak in Morris Run.
  • DEP meeting at night in Council Room to discuss Blossburg watersheds.

11-20
  • Water leak in Morris Run.

11-21
  • Finish work on water leak in Morris Run.
  • Put plaque on John Kuster's bench at Park.

11-22
  • Replace bulbs in Christmas lights. Have to order more bulbs.
  • Haul stone from Bloss Mountain for stockpile at garage.
  • Finish cleaning garages so equipment can be stored inside for winter.

11-23
  • Rain yesterday froze on roads overnight. Salt roads.

11-25
  • Replace water service line on S. Wmsn. Rd.
  • Work on Morris Run bill for water line repair.

11-26
  • Put up Christmas lights on Main St.
  • Install new conduit between spotlight poles at stp and wire lights so they work.
  • Listen for water leaks behind Low Income.

11-27
  • Sewer class at Wellsboro in morning.
  • Salt roads in morning after snowfall fast night.
  • Make access road to possible water leak behind Low income.